Regulation 67 of the Planning, Development and Infrastructure (General) Regulations 2017 states, when Planning Consent is granted, the applicant has 2 years from the operative date to obtain Building Rules Consent. When Development Approval is granted, the applicant has 2 years from the operative date to substantially commence the development, thereafter for the development to be substantially or fully completed within 3 years.
All extension of time requests for development applications lodged after 19 March 2021 are to be completed via the Plan SA Portal.
All extension of time requests for development applications lodged before 19 March 2021 are to be completed via the City of West Torrens Extension of Time request form (DPC or DA) Online Form.